Hi Friends,

Last week we talked about the dirt. This week: concrete.

Before the steel. Before the timber. Before the glass. The concrete was there first - holding it all.

Fair warning: this issue turned into an unintentional tribute to Winn Construction. They didn't ask for it, they earned it. When you repeatedly pour concrete on the same project for two years, you tend to show up in the photos.

Let's dig in.


Winn Construction crew preparing foundation forms surrounded by vertical rebar with orange safety caps at the Theodore Roosevelt Presidential Library. August 2023. Image © Chad Ziemendorf

First concrete pour at the Theodore Roosevelt Presidential Library. August 2023. Image © Chad Ziemendorf

First concrete pour at the Theodore Roosevelt Presidential Library. August 2023. Image © Chad Ziemendorf

The first concrete pour at the Theodore Roosevelt Presidential Library. Winn Construction crews prepare the foundation forms. August 2023. All images © Chad Ziemendorf.

The Perfect Mix

In August 2023, Winn Construction poured the first concrete at the Theodore Roosevelt Presidential Library.

It was not ordinary concrete.

The mix was developed specifically for this project - a low-carbon formula using fly ash and slag to replace a significant portion of the traditional cement. The result: roughly half the carbon footprint of a standard pour.

Dickinson Ready-Mix, a local supplier, worked with engineers to develop the formula. North Dakota concrete, mixed for a North Dakota project, optimized with the same level of intention as everything else on this project.


Worker in blue hardhat inspecting rebar placement before first pour. August 2023. Image © Chad Ziemendorf

Rebar at the ready before the first concrete pour in August 2023.

Workers watching as first concrete flows through pump hose into foundation forms. August 2023. Image © Chad Ziemendorf

Workers look on as the first concrete flows through the pump truck hose and fills the forms. August 2023.

Aerial view of first concrete pour progress in west building footings. August 2023. Image © Chad Ziemendorf

An overhead view of the first concrete pour progress in the footings of the west building. August 2023.

First Pour

I remember that first pour clearly.

There was a unique energy on site that day. A heightened sense of anticipation. After months of earthwork and preparation, the first structural elements were finally going into the ground.

Watching the concrete flow through the pump truck hose and fill those forms felt like a moment of celebration. Everyone knew what it meant. This project was no longer just a good idea. It was a landmark becoming tangible.

Over the next two years, I would photograph thousands of yards of concrete installation. Retaining walls. Roof decks. Gallery floors. Parking lots. But this one stood out.

First pours always do. They're the line between planning and permanence.


View from inside rebar cage as worker ascends in man-lift before September pour. Image © Chad Ziemendorf

A view from inside the rebar of the western-most wall as a worker ascends in his man-lift to make final preparations before the concrete pour. September 2023.

Elevated view from man-lift of massive retaining wall rebar and forms. September 2023. Image © Chad Ziemendorf

An elevated view from a man-lift of the giant retaining wall concrete forms. September 2023.

Worker signaling to crew below for tools while securing concrete forms. September 2023. Image © Chad Ziemendorf

A worker signals to the team below for a tool to secure the next section of concrete forms. September 2023.

The First Walls

The eastern retaining wall and western perimeter wall required hundreds of yards of concrete - a succession of massive pours that would anchor the building's relationship to the bluff.

Retaining walls do exactly what the name suggests: they retain. They hold back the earth. They create the terraced landscape that allows a building to nestle into terrain rather than dominate it.

This eastern retaining wall would eventually disappear behind the finished structure and be back-filled with dirt and some mechanical elements. No one will see it. But without it, nothing else works.


Winter concrete pour with crew working amid snow in western North Dakota. December 2023. Image © Chad Ziemendorf

Winter concrete pours in western North Dakota. The work doesn't stop. December 2023.

Worker checking level to ensure vertical rebar alignment in freezing December conditions. Image © Chad Ziemendorf

A worker checks a level to ensure the rebar is vertical. December 2023.

Sunrise over construction site with heated blankets protecting curing concrete. December 2023. Image © Chad Ziemendorf

Sunrise over the site. Heated blankets protect recent pours from freezing temperatures. December 2023.

Worker measuring precise spacing between rebar in winter conditions. December 2023. Image © Chad Ziemendorf

Measuring the distance between rebar. Precision that will be buried but not forgotten. December 2023.

December concrete pour with protective blankets staged nearby and workers in forms. Image © Chad Ziemendorf

A December pour with blankets staged and ready. Timing matters when concrete meets cold. December 2023.

Winter Work

Western North Dakota winters are not for the timid.

Temperatures usually drop below -20°F. Wind chills push it lower. Some construction projects need to pause until spring. While the last two winters have been favorably mild for construction, there still have been some chilly days.

Concrete curing is a chemical reaction that requires heat. Pour in freezing conditions without protection, and the water in the mix freezes before the cement can hydrate. The result is weak, crumbly, useless.

The solution: heated blankets, careful timing, and workers willing to do precision work in conditions that make every movement harder.


Braun Intertec technician filling sample canisters for concrete testing. February 2024. Image © Chad Ziemendorf

A Braun Intertec technician fills sample canisters for testing. Temperature, strength, consistency - verified before the pour cures. February 2024.

Four workers with hand trowels chasing the pour and finishing concrete in close succession. February 2024. Image © Chad Ziemendorf

Four workers chase the pour with hand trowels, finishing in close succession. February 2024.

Continued Foundations

By February 2024, the foundation work had expanded across the site. Each section of the building required its own carefully engineered footings - designed not just for structural loads but for the specific soil conditions of this place.

Remember the bentonite clay from last week? The same geology that makes this landscape so unusual also makes it challenging to build on. The foundations had to account for soil that swells when wet and contracts when dry.

Engineering for the earth, not against it.


Auditorium concrete structure silhouetted against Badlands sunrise. April 2024. Image © Chad Ziemendorf

Sunrise through the auditorium structure. The concrete skeleton awaits its skin. April 2024.

The Auditorium

By April 2024, the auditorium structure had risen far enough to catch the morning light.

This image is a subtle favorite of mine. The concrete skeleton silhouetted against the Badlands sunrise as seen from across the breezeway - a building becoming, not yet arrived. And a magical moment that I got to witness knowing that as soon as the perimeter walls were in place, it will never again be duplicated.

The auditorium will host lectures, films, and public programs. It will be a gathering place for ideas about citizenship, conservation, and leadership. But in April 2024, it was still just potential. Steel and concrete waiting for purpose.


Enjoying this? Boundless is a free weekly newsletter delivering behind-the-scenes documentation of the Theodore Roosevelt Presidential Library, plus reflections on what vast landscapes teach us about peace, resilience, perspective, and renewal.

Subscribe here → to get the next issue delivered to your inbox every Sunday.


Worker measuring for steel plate anchor placement at crisp April sunrise. April 2024. Image © Chad Ziemendorf

A worker measures for steel plate placement - an anchor point for a future beam. Crisp April sunrise. April 2024.

Workers on multiple lifts connecting concrete forms like sophisticated LEGO creations. April 2024. Image © Chad Ziemendorf

Workers on multiple lifts connect concrete forms like sophisticated LEGO creations. April 2024.

Concrete flowing into westernmost wall forms during afternoon pour. April 2024. Image © Chad Ziemendorf

The pour, the next afternoon. April 2024.

The Forms

Concrete doesn't shape itself. Every curve, every edge, every surface texture is determined by the forms it's poured into.

The formwork for this project was not simple. Snøhetta's design called for curves and angles that required custom fabrication. Standard plywood wouldn't do.

What you see here is the preparation for one of the major structural walls - forms set with precision, braced against the pressure of wet concrete, ready to receive thousands of pounds of material that will cure into something permanent.

The forms come down. The wall remains.


Worker crouching with mason's line to ensure rebar grid is level across living roof deck. August 2024. Image © Chad Ziemendorf

Setting the rebar grid on the future living roof deck. A mason's line ensures precision across the expanse. August 2024.

Rooftop Rebar

By 2024, the work had moved upward.

The living roof - the same surface that would eventually receive the preserved topsoil from Issue 002 - required its own concrete deck. Before that deck could be poured, the rebar had to be set.

This worker is using a mason's line to ensure the steel grid maintains the roof's designed curve. On a surface this large, small deviations compound. The line keeps every section true to the arc.

Precision work, holding the curve.


Concrete pump boom extending across roof surface. October 2024. Image © Chad Ziemendorf

The pump boom reaches across the roof surface. October 2024.

Worker hand-finishing roof deck concrete. October 2024. Image © Chad Ziemendorf

Hand-finishing the roof deck concrete. October 2024.

Boom arm delivering concrete at sunrise with workers and mechanical screed in background. October 2024. Image © Chad Ziemendorf

The boom arm delivers concrete at sunrise as workers smooth the pour with a mechanical screed in the background. October 2024.

Rooftop Pours

The roof deck pours happened in the back half of 2024 - varying temperatures, varying wind, still demanding.

Concrete pumps extended their booms across the surface, delivering material to crews who spread and leveled it by hand. The work moved fast. Concrete waits for no one. Once the pour begins, you finish or you lose it.

This deck would eventually support thousands of pounds of growing medium, native plants, and visitors walking the rooftop path. But first it had to cure. First it had to hold.


Worker hand-troweling concrete floor in first-floor gallery area. January 2025. Image © Chad Ziemendorf

Hand-finishing concrete in one of the first-floor gallery areas. January 2025.

Office Work

Not all concrete work happens where visitors will go.

The administrative areas - offices, workrooms, back-of-house spaces - required their own pours. These floors will support the people who keep the library running long after the cameras leave.

This worker is hand-troweling the surface in one of those spaces. Same precision. Same care. Whether the floor sees a thousand visitors a day or a handful of staff.


Masonry crew filling cinder block cores with grout. March 2025. Image © Chad Ziemendorf

The masonry crew fills cinder block cores with grout. Structural work that will be hidden behind finished walls. March 2025.

Masonry

Concrete takes many forms.

Here the Hardscapes Plus crew fills the cores of cinder blocks with grout - strengthening walls that will protect mechanical elements. This work won't be visible in the finished building. It will be behind drywall, behind finishes, behind the surfaces visitors actually see.

But it will be holding things up. Quietly. Permanently.


Workers pouring concrete floor in main gallery space. March 2025. Image © Chad Ziemendorf

Workers pouring concrete floor in main gallery space. March 2025.

Worker smoothing gallery floor concrete with long-handled finishing tool. March 2025. Image © Chad Ziemendorf

Worker smoothing gallery floor concrete with long-handled finishing tool. March 2025.

Interior Floors

The main gallery floors went down in April 2025. Large pours that required coordination between multiple crews - concrete trucks arriving on schedule, pumps positioned, workers ready to spread and finish before the material began to set.

These are the floors visitors will actually walk on. The ones beneath their feet as they encounter Roosevelt's life, his presidency, his legacy. Every step supported by work done in a single day, two years before opening.


Worker with grinder smoothing concrete edges along rooftop walkway walls. April 2025. Image © Chad Ziemendorf

A worker grinds down the concrete edgework along the rooftop walkway walls. April 2025.

Finishing Details

By June 2025, some areas of the work had shifted from pouring to finishing.

The rooftop walkway will guide visitors across the living roof, offering views of the Badlands in every direction. Before the tile could be laid, the concrete beneath it had to be perfect.

Here, a worker grinds the edges where forms met concrete - removing high spots, preparing the surface for the finish to come. It's detail work. The kind of task that separates adequate from excellent.

Details that seem small. Details that matter.


Winn Construction crew pouring visitor parking lot concrete. April 2025. Image © Chad Ziemendorf

Winn Construction crews pour the visitor parking area. April 2025.

Parking and Site Work

The building structure itself was nearly complete by July 2025. But concrete work continued.

Visitor parking. Service areas. The countless surfaces that support a building's operation without being part of the building itself. Winn Construction - the same crew that poured the first foundation in August 2023 - was still on site, still pouring, still doing the necessary work.

From first foundation to final parking lot: nearly two full years of concrete.


Concrete pylons dotting hillside awaiting steel bridge with library rising in background. June 2025. Image © Chad Ziemendorf

Concrete pylons dot the hillside, waiting for the steel bridge that will connect one of the boardwalk's most dramatic sections. The library rises in the background. June 2025.

Boardwalk Foundations

The 1-mile boardwalk loop extends from the library into the surrounding terrain, connecting to over 100 miles of trails. Its pylons required their own foundations - concrete anchors sunk into the earth to support the path that will carry visitors into the landscape.

This is where the building meets the land. Where architecture becomes trail. Where structure gives way to exploration.

The concrete here doesn't hold up a building. It holds up an invitation.


Sunrise through boardwalk pylon silhouettes with Badlands beyond. July 2025. Image © Chad Ziemendorf

Sunrise over the roof of the Theodore Roosevelt Presidential Library with the boardwalk pylons seen in the foreground. The necessary work, finished. Ready for what comes next. July 2025.

The Necessary Work

From the first foundation in August 2023 to the parking lots in 2025, Winn Construction showed up. Pour after pour. Season after season. The work beneath the work.

Steve Fore, JE Dunn's General Superintendent, put it this way: "We're not just preserving history here. We're building history for someone else to preserve."

The steel gets the skyline. The timber gets the warmth. The glass gets the light.

But the concrete was there first. Holding it all.


Steel beam placement in 2025. Worker on lift guiding beam into position with concrete walls in background. Image © Chad Ziemendorf

Steel beam placement in 2025. Next week, the steel structure rises from the Badlands. That's some nice concrete in the background.

Next Week

The steel that made the Library possible. How True North Steel and Innovative Builders created the skeleton for North Dakota's most ambitious structure.

See you next Sunday.

Chad Z.

P.S. - If Boundless is resonating, forward it to someone who might enjoy it. A friend in construction. A colleague who appreciates craft. Someone who understands that the work no one sees is often the work that matters most.


Morning Sanctuary - Panoramic view of Theodore Roosevelt Presidential Library at sunrise with Badlands landscape. Image © Chad Ziemendorf

"Morning Sanctuary." One of my newest and most calming images. Coming soon to the new print shop (currently in development).


Want More Like This?

If you appreciate this level of landmark project documentation, or if you're drawn to what vast landscapes teach us about peace, resilience, perspective, and renewal, Boundless might be for you.

New issues arrive every Sunday through the library's opening day, July 4, 2026.

Subscribe to Boundless →


Boundless is the weekly newsletter of photographer Chad Ziemendorf. Each issue explores what vast landscapes and landmark human endeavors teach us about peace, resilience, perspective, and renewal.

I'm a contractor documenting this project, not an expert on construction. The opinions here are mine alone. And while I do my best to get the details right, I can't guarantee perfect accuracy on every technical point. If something's off, let me know.

All content and images © Chad Ziemendorf. All rights reserved.

More From The Journal

Recent thoughts on craft, process, and the work where monumental human endeavors meet vast, quiet landscapes - including the latest from my Boundless newsletter.

View all

Boundless No. 00005 // Steel Rising
  • by Chad Ziemendorf

Boundless No. 00005 // Steel Rising

This article was originally published as a Boundless newsletter. New issues arrive every Sunday. Subscribe here  ·  Read previous issues Today we're going to chat about steel. As you scroll through this issue, watch how each phase of the construction process depended...

Read more

Boundless No. 00004 // An Exhale For Your Soul
  • by Chad Ziemendorf

Boundless No. 00004 // An Exhale For Your Soul

Boundless subscribers read this first. New issues arrive every Sunday. Subscribe here  ·  Read previous issues Today's issue is an exhale for your soul. If you've been running hard lately, if the winter has felt long (and if you're reading this from...

Read more

Boundless No. 00003 // Anchored To The Earth
  • by Chad Ziemendorf

Boundless No. 00003 // Anchored To The Earth

  Hi Friends, Last week we talked about the dirt. This week: concrete. Before the steel. Before the timber. Before the glass. The concrete was there first - holding it all. Fair warning: this issue turned into an unintentional tribute...

Read more

Boundless No. 00002 // But First, Dirt
  • by Chad Ziemendorf

Boundless No. 00002 // But First, Dirt

  Today's issue is about something most people dismiss before they've even thought about it. And how the team building the TR Library refused to make that mistake. Let's dig in. Bentonite clay and scoria fragments off of Magpie Road,...

Read more

Boundless No. 00001 // The Exhale
  • by Chad Ziemendorf

Boundless No. 00001 // The Exhale

  Welcome to the first issue of Boundless. This was first emailed to subscribers on Sunday January 18, 2026. Housekeeping: Some of you might still be receiving the Welcome Series if you signed up recently. This is the first issue...

Read more

Help TR Library Make It On The Cover of ENR Magazine
  • by Chad Ziemendorf

Help TR Library Make It On The Cover of ENR Magazine

Originally published as a landing page during the ENR Magazine photo contest in January of 2026. Contest will end on January 22, 2026, some links below may no longer work after the voting closes. Help TR Library Make It On...

Read more